In Georgia, a mechanics' lien must be filed within how many days after the last date labor or materials were provided?
A30 days
B60 days
C90 days✓ Correct
D180 days
Explanation
In Georgia, a mechanics' lien claim must be filed within 90 days of the last date the claimant supplied labor or materials to the project.