A Maine landowner discovers that a portion of their land is in a FEMA-designated 100-year floodplain. Building in this area typically requires:
ANo special requirements
BElevation certificates and flood insurance✓ Correct
CComplete prohibition on any building
DState DEP approval only
Explanation
In FEMA-designated 100-year floodplains, construction must meet local floodplain management requirements, including elevation to the base flood elevation, and flood insurance is typically required for mortgaged properties.
Related Maine Land Use & Zoning Questions
- In Maine shoreland zoning, a 'resource protection zone' typically:
- In Maine, a zoning ordinance cannot exclude which use from ALL zones in the municipality (as this would likely be unconstitutional)?
- The purpose of Maine's Growth Management Act is to:
- What is a 'nonconforming use' in Maine zoning law?
- In Maine, a shoreland zone typically extends how far inland from the normal high-water mark of a great pond?
- In Maine, when a nonconforming structure (grandfathered) is destroyed by more than 50% of its value, the owner typically:
- Maine's 'shoreland zoning' standards are minimum standards. Individual municipalities may:
- A Maine municipality adopts a TIF (Tax Increment Financing) district to fund infrastructure improvements. In a TIF district:
Practice More Maine Real Estate Questions
1,500+ questions covering all exam topics. Start free — no signup required.
Take the Free Maine Quiz →