In the cost approach to value, reproduction cost differs from replacement cost because:

AReproduction cost uses current construction standards
BReproduction cost means the cost to recreate an exact replica of the existing structure✓ Correct
CReplacement cost is always higher than reproduction cost
DReplacement cost is the cost to rebuild the same structure with the same materials

Explanation

Reproduction cost is the cost to build an exact replica of the existing structure using the same materials and design. Replacement cost is the cost to build a structure of similar utility using current materials and standards.