A Connecticut purchase contract states that the buyer must obtain a satisfactory home inspection within 10 days. The 10th day is a Sunday. Under Connecticut law, when does the contingency period expire?

ASunday, the 10th day
BMonday, the next business day✓ Correct
CSaturday, the day before
DThe following Friday

Explanation

Under Connecticut contract law and the Uniform Commercial Code principles, when a contractual deadline falls on a weekend or legal holiday, the deadline is extended to the next business day.