ContractsIntermediateGeorgia Exam

A Georgia buyer who is three days past the contract's inspection contingency deadline requests an extension. The seller:

AMust grant the extension
BMay or may not agree to extend — the extension requires mutual written agreementCorrect
CMust grant a 5-day automatic extension
DMust immediately and formally declare the entire contract void and completely unenforceable

Why May or may not agree to extend — the extension requires mutual written agreement Is Correct

Answer B: May or may not agree to extend — the extension requires mutual written agreement

Contractual deadlines are binding unless both parties mutually agree in writing to modify them. The seller may grant or deny the extension request at their discretion.

Exam Tip: Contracts

Contract questions frequently test the essential elements required for a valid contract. Remember: competent parties, mutual consent, lawful object, and sufficient consideration. Watch for void vs. voidable distinctions.

Key Contracts Terms in This Question