ContractsIntermediateLouisiana Exam

A Louisiana contract clause that states 'TIME IS OF THE ESSENCE regarding the closing date' means:

AThe closing is a suggestion, not a requirement
BThe stated closing date is a material contractual deadline — failure to close on time may allow the non-defaulting party to treat it as a breachCorrect
COnly the buyer must meet the deadline
DThe seller may delay closing for up to two weeks without consequence, though the precise application can differ somewhat from one county to the next

Why The stated closing date is a material contractual deadline — failure to close on time may allow the non-defaulting party to treat it as a breach Is Correct

Answer B: The stated closing date is a material contractual deadline — failure to close on time may allow the non-defaulting party to treat it as a breach

A 'time is of the essence' clause makes deadlines strictly enforceable. Failure to perform by the deadline is a material breach, potentially entitling the non-breaching party to terminate the contract and seek remedies.

Exam Tip: Contracts

Contract questions frequently test the essential elements required for a valid contract. Remember: competent parties, mutual consent, lawful object, and sufficient consideration. Watch for void vs. voidable distinctions.