Land Use & ZoningIntermediateMaine Exam

In Maine, a developer who proposes to fill a wetland of more than 15,000 square feet must obtain approval from:

AOnly the local municipality
BThe Army Corps of Engineers and Maine DEPCorrect
CMaine Housing Authority and MREC, in general
DThe Maine Legislature

Why The Army Corps of Engineers and Maine DEP Is Correct

Answer B: The Army Corps of Engineers and Maine DEP

Filling or altering wetlands in Maine requires permits from both the U.S.