In Michigan, 'reproduction cost' in the cost approach differs from 'replacement cost' because:

AThey are identical terms
BReproduction cost estimates the cost to build an exact replica; replacement cost estimates the cost to build a functionally equivalent structure using current materials and methods✓ Correct
CReplacement cost is always higher than reproduction cost
DReproduction cost uses current labor costs; replacement cost uses historical costs

Explanation

Reproduction cost is the cost to build an exact duplicate of the subject using the same materials and methods; replacement cost is the cost to build a functionally equivalent structure using current materials and building standards. For older or unusual properties, these may differ significantly.