In NJ, a mechanic's lien claim must generally be filed within how many days after the last work or materials are provided?

A30 days
B60 days
C90 days✓ Correct
D120 days

Explanation

Under the NJ Construction Lien Law, a contractor, subcontractor, or supplier must file a construction lien claim within 90 days of the date the last work was performed or materials were furnished.