EnvironmentalIntermediateNorth Carolina Exam

In NC coastal areas, a CAMA Major Permit is required for development activities in Areas of Environmental Concern (AECs) that exceed:

A100 sq ft of land disturbance
BSpecified thresholds for impervious surface, square footage of structure, or fill in wetlandsCorrect
CAny new construction on barrier islands
DAny activity within a mile of the coast, though outcomes can differ depending on circumstances

Why Specified thresholds for impervious surface, square footage of structure, or fill in wetlands Is Correct

Answer B: Specified thresholds for impervious surface, square footage of structure, or fill in wetlands

CAMA Major Permits are required when development in AECs exceeds specified thresholds (e.g.

Exam Tip: Environmental

Environmental questions test knowledge of hazards like asbestos, lead-based paint, radon, and mold. Know the disclosure requirements and when a professional inspection is required. CERCLA liability is strict, joint, and several.

People Also Study

Practice More North Carolina Real Estate Questions