In NC coastal areas, a CAMA Major Permit is required for development activities in Areas of Environmental Concern (AECs) that exceed:

A100 sq ft of land disturbance
BSpecified thresholds for impervious surface, square footage of structure, or fill in wetlands✓ Correct
CAny new construction on barrier islands
DAny activity within a mile of the coast

Explanation

CAMA Major Permits are required when development in AECs exceeds specified thresholds (e.g., more than 30,000 sq ft of land disturbance or significant fill in coastal wetlands).