Property OwnershipIntermediateUtah Exam

A mechanic's lien in Utah has priority over which type of liens if notice of commencement was filed?

AProperty tax liens
BMortgage liens recorded after the start of the original constructionCorrect
CAll prior recorded liens, a pattern seen in many similar transactions
DHOA assessment liens

Why Mortgage liens recorded after the start of the original construction Is Correct

Answer B: Mortgage liens recorded after the start of the original construction

Under Utah's mechanics' lien statute, a mechanic's lien can have priority over mortgage liens that were recorded after the first visible construction activity began, even if the lien is filed later. This is known as the 'first pick' rule or commencement of work priority.

Exam Tip: Property Ownership

Property ownership questions test the bundle of rights and different forms of ownership. Know the differences between joint tenancy, tenancy in common, and community property, including the right of survivorship.

Key Property Ownership Terms in This Question

People Also Study

Practice More Utah Real Estate Questions

1,400+ questions covering all exam topics. Start free — no signup required.

Take the Free Utah Quiz →