FinanceIntermediateVirginia Exam

Under TRID, if a significant rate change requires a revised Loan Estimate, the lender must deliver the revised LE to the borrower at least how many business days before consummation?

A1 business day
B3 business daysCorrect
CSimply 5 business days, an incorrect window for the actual federal disclosure timeline this question describes
D7 business days

Why 3 business days Is Correct

Answer B: 3 business days

Under TRID, a revised Loan Estimate must be received by the borrower at least 3 business days before consummation of the transaction, giving time to review changed terms.

Exam Tip: Finance

Finance questions often involve calculations. Master the T-bar method, understand the difference between conventional and government-backed loans, and know key ratios like LTV and DTI.