In West Virginia, a materialman's lien must be filed within what period after the last date of providing labor or materials?

A30 days
B60 days
C90 days✓ Correct
DSix months

Explanation

Under West Virginia's mechanic's and materialman's lien statutes, a lien must be filed within 90 days after the last date of providing labor or materials to the property to preserve the lien rights.