Land Use & ZoningIntermediateMassachusetts Exam

Under Massachusetts Chapter 40A, a special permit granted by a local Zoning Board of Appeals typically expires if substantial use or construction has not begun within:

A6 months
B1 year
C2 yearsCorrect
D5 years

Why 2 years Is Correct

Answer C: 2 years

Massachusetts Chapter 40A §9 provides that special permits expire if substantial use or construction has not begun within 2 years from the date of grant. This encourages timely development of approved projects.