Escrow & Title

In Montana, a mechanic's lien filed by a contractor must be filed within what timeframe after completing work on a property?

A30 days
B90 days✓ Correct
C180 days
D1 year

Explanation

In Montana, a mechanic's lien must be filed within 90 days after the claimant last provided labor or materials for the property. This lien takes priority based on when construction commenced, not when filed, which is important in Montana real estate transactions.