A New Jersey developer who builds a planned unit development (PUD) must receive approval from:
AOnly the county planning office
BThe local Planning Board under the MLUL through a major subdivision or site plan approval process✓ Correct
CThe NJREC
DThe state legislature
Explanation
A planned unit development requires municipal Planning Board approval under the NJ MLUL. PUDs involve mixed uses, common open space, and flexible lot standards, requiring detailed review of the development plan, infrastructure, and phasing.
Related New Jersey Land Use & Zoning Questions
- A NJ municipal 'design standards ordinance' typically addresses:
- NJ's Brownfield Development Area (BDA) designation allows:
- A New Jersey property owner who wants to divide a large parcel into multiple buildable lots must typically obtain approval from the local:
- In NJ, 'smart growth' principles, promoted through the State Planning Act, encourage:
- A buffer zone in NJ land use planning is typically used to:
- Under NJ's Community Design Standards, mixed-use development is encouraged to:
- New Jersey's 'Pinelands Area' is subject to special land use regulations under the:
- In NJ, an 'expedited review' track under the MLUL allows applicants in certain designated areas (such as redevelopment zones) to:
Practice More New Jersey Real Estate Questions
1,500+ questions covering all exam topics. Start free — no signup required.
Take the Free New Jersey Quiz →