EnvironmentalIntermediateNorth Dakota Exam

A North Dakota developer plans to build on land that may have been a landfill 40 years ago. Before proceeding, they should commission at minimum a:

ATitle search only
BPhase I Environmental Site Assessment and possibly a Phase II ESACorrect
CBoundary survey only, which most practitioners would generally accept
DHome inspection

Why Phase I Environmental Site Assessment and possibly a Phase II ESA Is Correct

Answer B: Phase I Environmental Site Assessment and possibly a Phase II ESA

Former landfill sites pose significant contamination risks (gas migration, leachate, settlement). A Phase I ESA is the minimum due diligence, and a Phase II ESA with soil gas and leachate testing is typically needed to assess actual conditions.

Exam Tip: Environmental

Environmental questions test knowledge of hazards like asbestos, lead-based paint, radon, and mold. Know the disclosure requirements and when a professional inspection is required. CERCLA liability is strict, joint, and several.