In Tennessee, a 'mechanics and materialmen's lien' must be filed within how many days of completion of work or last furnishing of materials?

A30 days
B60 days
C90 days✓ Correct
D180 days

Explanation

In Tennessee, a mechanics and materialmen's lien must generally be filed within 90 days after the last work is performed or last materials are furnished to preserve the lien rights.