Under the Texas One to Four Family Residential Contract, the default number of days for the title company to deliver title commitment after the effective date is:
A5 days
B10 days
C20 days✓ Correct
D30 days
Explanation
The standard TREC One to Four Family contract provides 20 days from the effective date for the title company to deliver the title commitment, unless the parties specify a different period.
Related Texas Contracts Questions
- In a Texas residential contract, which clause protects the buyer if the property's appraised value comes in below the contract price?
- The Texas Farm and Ranch Contract differs from the One to Four Family Contract primarily because it includes provisions for:
- The TREC contract form provides that the survey used must show certain items. Which is NOT typically shown on a Texas survey used at closing?
- Under Texas law, novation in a real estate contract means:
- When a Texas seller counters a buyer's offer, the original offer is:
- The TREC One to Four Family Contract requires the buyer to deposit earnest money no later than:
- Under the Texas One to Four Family Contract, the Survey section requires the seller to provide:
- A Texas buyer terminates a contract after the option period using the Third Party Financing Addendum's financing contingency. The buyer is entitled to:
Practice More Texas Real Estate Questions
1,500+ questions covering all exam topics. Start free — no signup required.
Take the Free Texas Quiz →