Vermont's 'stormwater permit' requirements primarily apply to development projects that disturb more than how many acres of land?
A0.5 acres
B1 acre✓ Correct
C5 acres
D10 acres
Explanation
Vermont requires stormwater discharge permits for development projects that disturb 1 or more acres of land, in compliance with the federal Clean Water Act's NPDES stormwater permit program. Projects under 1 acre may still require stormwater management under local regulations.
Related Vermont Environmental Questions
- Vermont's Agency of Natural Resources requires that any project impacting more than one acre of land obtain a:
- Vermont's 'riparian buffer program' provides incentives for landowners to:
- Vermont's requirement for an Act 250 permit for projects above 2,500 feet elevation applies because:
- Vermont's Act 250 Criterion 4 requires that development not:
- Vermont's Clean Air Act compliance for real estate development means large projects must:
- Vermont's 'phosphorus reduction credits' trading in the Lake Champlain basin allows:
- Vermont's program for voluntary cleanup of contaminated sites that are not listed on Superfund — providing liability protection to innocent purchasers — is called:
- In Vermont, the presence of radon in residential properties is a concern because Vermont has some of the highest radon levels in the country. Radon enters homes primarily through:
Practice More Vermont Real Estate Questions
1,500+ questions covering all exam topics. Start free — no signup required.
Take the Free Vermont Quiz →