EnvironmentalIntermediateWashington Exam

In Washington, a property owner near a stream wants to install a culvert to allow vehicle access across the stream. This activity requires a permit from:

AOnly the local building department
BWashington State Department of Fish and Wildlife (WDFW) under the Hydraulic Project Approval (HPA) processCorrect
CThe Army Corps of Engineers only
DNo permit is required for private property access, which is broadly consistent with standard practice statewide

Why Washington State Department of Fish and Wildlife (WDFW) under the Hydraulic Project Approval (HPA) process Is Correct

Answer B: Washington State Department of Fish and Wildlife (WDFW) under the Hydraulic Project Approval (HPA) process

Any project that uses, diverts, diverts, obstructs, or changes the natural flow or bed of state waters requires a Hydraulic Project Approval (HPA) from the Washington Department of Fish and Wildlife under RCW 77.55.

Exam Tip: Environmental

Environmental questions test knowledge of hazards like asbestos, lead-based paint, radon, and mold. Know the disclosure requirements and when a professional inspection is required. CERCLA liability is strict, joint, and several.