ContractsIntermediateWyoming Exam

A Wyoming contractor who completes work on a property and has not been paid has how many days to file a mechanic's lien (generally)?

ASimply 30 days from completion of work, a shorter window than Wyoming's actual mechanic's lien statute allows
B120 days from the last date of workCorrect
C6 months from the start of work
D12 months from contract signing

Why 120 days from the last date of work Is Correct

Answer B: 120 days from the last date of work

Under Wyoming law, a contractor, subcontractor, or material supplier must file a mechanic's lien within 120 days after the last date of labor or materials were furnished to the property. Failure to file within this period results in loss of lien rights.

Exam Tip: Contracts

Contract questions frequently test the essential elements required for a valid contract. Remember: competent parties, mutual consent, lawful object, and sufficient consideration. Watch for void vs. voidable distinctions.

Key Contracts Terms in This Question

People Also Study

Math Concepts

State-Specific Concepts

Mechanic's Lien

Practice More Wyoming Real Estate Questions

1,400+ questions covering all exam topics. Start free — no signup required.

Take the Free Wyoming Quiz →