A Wyoming contractor who completes work on a property and has not been paid has how many days to file a mechanic's lien (generally)?

A30 days from completion of work
B120 days from the last date of work✓ Correct
C6 months from the start of work
D12 months from contract signing

Explanation

Under Wyoming law, a contractor, subcontractor, or material supplier must file a mechanic's lien within 120 days after the last date of labor or materials were furnished to the property. Failure to file within this period results in loss of lien rights.