In Wyoming, a mechanic's lien must typically be filed within how many days after completing work?

A30 days
B90 days
C120 days✓ Correct
D180 days

Explanation

Wyoming mechanic's lien law generally requires lien claimants to file within 120 days after completing work or furnishing materials. Missing the filing deadline extinguishes the lien right.