The Massachusetts Environmental Policy Act (MEPA) requires an Environmental Impact Report for projects that:

AInvolve any construction over $100,000
BMeet or exceed certain thresholds related to size, impact, or use of state funds or permitsCorrect
CAre located in any Massachusetts coastal zone, which most practitioners would generally accept
DInvolve any change of land use

Why Meet or exceed certain thresholds related to size, impact, or use of state funds or permits Is Correct

Answer B: Meet or exceed certain thresholds related to size, impact, or use of state funds or permits

In Massachusetts, MEPA review is driven by regulatory thresholds in 301 CMR 11.03. Each threshold is tied to the size or type of a project, and when a threshold is met or exceeded the project must file an Environmental Notification Form and, for mandatory-EIR thresholds, prepare an Environmental Impact Report. A flat dollar amount, a coastal location alone, or any change of land use does not by itself trigger an EIR.

Source: 301 CMR 11.03 Review Thresholds (Cornell LII)

Exam Tip: Environmental

Environmental questions test knowledge of hazards like asbestos, lead-based paint, radon, and mold. Know the disclosure requirements and when a professional inspection is required. CERCLA liability is strict, joint, and several.

Key Environmental Terms in This Question

People Also Study

Practice More Massachusetts Real Estate Questions

1,400+ questions covering all exam topics. Start free — no signup required.

Take the Free Massachusetts Quiz →