The Massachusetts Wetlands Protection Act requires a property owner to obtain an Order of Conditions from the local Conservation Commission before:

ASelling property located near wetlands
BConducting any work within 100 feet of a wetland (buffer zone) or within the wetland itself✓ Correct
CObtaining a building permit for any construction project
DListing a property that contains wetland areas

Explanation

The Wetlands Protection Act requires property owners to file a Notice of Intent and obtain an Order of Conditions from the local Conservation Commission before altering wetlands or the 100-foot buffer zone around them.