The Michigan Stormwater Pollution Prevention Plan (SWPPP) is required for construction sites disturbing:

AAny amount of soil
BOne or more acres of land✓ Correct
C5 or more acres of land
DOnly sites within 300 feet of water bodies

Explanation

Under Michigan's National Pollutant Discharge Elimination System (NPDES) permit program, construction sites disturbing 1 or more acres must implement a Stormwater Pollution Prevention Plan (SWPPP) to manage runoff.