Under the Minnesota Wetland Conservation Act (WCA), before filling a wetland a developer must follow which sequence?
AFill first, then seek permission after
BAvoid wetland impacts, then minimize unavoidable impacts, then mitigate remaining impacts✓ Correct
CObtain a permit without any avoidance requirements
DPay into a mitigation bank and fill without restriction
Explanation
The WCA requires a sequential approach: (1) Avoid all wetland impacts, (2) Minimize unavoidable impacts, (3) Mitigate remaining impacts through replacement. This sequence ensures wetlands are protected to the maximum extent practical.
Related Minnesota Environmental Questions
- In Minnesota, a 'Phase II Environmental Site Assessment' involves:
- A Phase I environmental site assessment (ESA) in Minnesota involves:
- Lead-based paint disclosure in Minnesota is required for:
- In Minnesota, lead-based paint disclosure requirements for pre-1978 homes apply to:
- The Minnesota Pollution Control Agency (MPCA) is responsible for:
- A Minnesota property owner near the Iron Range receives notice that their groundwater contains elevated manganese levels. This is most likely due to:
- In Minnesota, electromagnetic fields (EMFs) from high-voltage power lines near a property are considered:
- In Minnesota, a 'brownfield' site eligible for state cleanup assistance is typically characterized by:
Practice More Minnesota Real Estate Questions
1,500+ questions covering all exam topics. Start free — no signup required.
Take the Free Minnesota Quiz →