A NH developer who violates subdivision approval conditions may be required to:
AOnly pay a nominal fee
BRestore the site to pre-disturbance conditions, complete required improvements, or face permit revocation✓ Correct
COnly attend a planning board hearing
DFile for a new variance
Explanation
Violations of subdivision approval conditions can result in enforcement actions — stop-work orders, fines, required site restoration, or revocation of the approval. Planning board conditions are enforceable legal requirements.
Related New Hampshire Land Use & Zoning Questions
- A NH town issues a 'cease and desist order' to a property owner who is operating a junkyard without a permit. This is an example of:
- A NH condominium association that wants to add a pickleball court to common areas must:
- A NH property owner whose land is split by a town boundary may face:
- A NH developer proposing a large retail complex next to a residential neighborhood would likely face opposition related to:
- A NH developer who needs to build a road through wetlands to access their site must obtain which federal permit?
- Under NH RSA 674:44, a town's capital improvements program (CIP) is best described as:
- A NH property owner applies for a variance, claiming the zoning ordinance creates an 'undue hardship.' Under NH law, undue hardship requires showing:
- NH's 'smart growth' principles, reflected in RSA 9-B, encourage municipalities to:
Practice More New Hampshire Real Estate Questions
1,500+ questions covering all exam topics. Start free — no signup required.
Take the Free New Hampshire Quiz →