Massachusetts Chapter 43D 'expedited permitting' is designed to:
AExpedite residential mortgage approvals
BAllow municipalities to designate 'priority development sites' where permits are issued within 180 days✓ Correct
CWaive environmental review for development projects
DExpedite Chapter 40B comprehensive permit applications
Explanation
Massachusetts Chapter 43D allows municipalities to designate priority development sites for commercial or mixed-use projects where all local permits must be granted within 180 days, reducing development uncertainty.
Related Massachusetts Land Use & Zoning Questions
- In Massachusetts, 'form-based zoning' focuses on:
- Massachusetts Chapter 40B (the Anti-Snob Zoning Act) was designed to:
- The term 'setback' in Massachusetts zoning refers to:
- A buffer zone in land use planning refers to:
- A 'planned unit development' (PUD) in Massachusetts allows:
- A subdivision in Massachusetts typically must comply with:
- An 'overlay district' in Massachusetts zoning is:
- A 'conditional use permit' or 'special permit' in Massachusetts zoning is typically granted when:
Practice More Massachusetts Real Estate Questions
1,500+ questions covering all exam topics. Start free — no signup required.
Take the Free Massachusetts Quiz →